This problem is compounded by the fact that these large projects are being carried out in multiple contractor organizations, each of which employs its own peculiar planning and control system (Frame, 2002).
By the early 1960s, it became increasingly apparent that the Defense Department was no longer able to track the efforts of its contractors with accuracy. It decided that contractors on large, complex projects should be required to report their project efforts in a consistent fashion. It worked to develop rules for reporting project progress and in 1967 issued Department of Defense Instruction (DODI) 7000.2, known also as the Cost/Schedule Control System Criteria (C/SCSC). In 1972, the Defense Department issued its Joint Implementation Guide, which gave practical advice on how to implement DODI 7000.2.The focus of the earned value system was the development of consistency and management discipline in contractor organizations in five areas:
Organization. Instructions are provided on the development of work breakdown structures and organizational breakdown structures.
Planning. Key planning requirements are highlighted -- for example, the establishment of performance baselines.
Accounting. Requirements are specified for the collection and maintenance of cost accounting data.
Analysis. Guidance is offered on use of earned value techniques for reporting budget variance, schedule variance, and EAC.
Reporting. Instructions are given on reporting project status through cost performance reports (CPRs), which are required on very large projects, or cost and schedule status reports (C/SSRs), which are less burdensome to generate than CPRs and are required on smaller projects.
In the 1990s, the earned value approach as promulgated by the Defense Department underwent a number of modifications. In 1991, DODI 7000.2 was superseded by DODI 5000.2, which was in turn was superseded by DOD Regulation (DODR) 5000.2-R in 1996. The Joint Implementation Guide was revised and replaced by a document titled Earned Value Management Implementation Guide in 1997. The current version of the earned value management system is designed to be less bureaucratic than its predecessors. It focuses less on mandating certain actions and more on providing guidelines (Frame, 2002).
According to Straight, Lawler and Schwartz (2003), earned-value management is not a new concept; however, the newly revised Office of Management and Budget (OMB) Circular a-11, Preparation, Submission, and Execution of the Budget may represent the first opportunity many government managers have had to work with these techniques. In this regard, Frame (2002) advises that, "In the 1990s, the earned value approach as promulgated by the Defense Department underwent a number of modifications. In 1991, DODI 7000.2 was superseded by DODI 5000.2, which was in turn was superseded by DOD Regulation (DODR) 5000.2-R in 1996. The Joint Implementation Guide was revised and replaced by a document titled Earned Value Management Implementation Guide in 1997" (p. 290). The current version of the earned value management system that is in place was intended to be less bureaucratic than its predecessors and concentrates less on mandating certain actions and more on providing guidelines (Frame, p. 290).
Because of the big-project focus of the Defense Department's approach to earned value management, coupled with many managers' unfamiliarity with the process, organizations outside of the defense community were unaware of its potential usefulness on nondefense projects. This situation began to change in the late 1980s. The earned value approach can be used effectively on small projects when bureaucratic requirements -- such as those found in DODI 7000.2, DODI 5000.2, and DODR 5000.2-R -- are stripped away. Today, most project management leaders in high-performing organizations acknowledge the great contribution the earned value method can offer them in planning, executing, and controlling their projects (Frame, 2002).
For federal agencies, Circular a-11 requires the use of an earned-value approach them to monitor and manage their capital asset projects' information technology, buildings, structures, major rehabilitation, land, vehicles, furniture, and equipment. In addition, Circular a-11 requires agencies to submit, as part of their annual budgets, a capital asset plan and business case (see proforma Exhibit 300 at Appendix ____) for each capital asset project. Completing the exhibits requires calculating the earned value for each project (Straight et al.). In this regard, Circular a-11 states that, "Earned value management (EVM) is a project (investment) management tool effectively integrating the investment scope of work with schedule and cost elements for optimum investment planning and control. The qualities and operating characteristics of earned value management systems (EVMS) are described in American National Standards Institute (ANSI)/Electronic Industries Alliance (EIA) Standard -748-1998, Earned Value Management Systems, approved May 19, 1998. It was reaffirmed on August 28, 2002" (p. 579).
Table 1.
Performance Management Thresholds
Contract Total Estimated Value, Then-Year $ (Note 1)
EVM Implementation (Notes 2,3,4,5,6,7,8)
CPR
Data Item
Note...
Project Management, Performance, and ClosureSchedule Variance (SV)SV = Earned Value – Planned CostSV = $600 - $540SV = $60The earned value refers to the accomplishment of physical, financial units from the project activities. The difference between the earned value and the planned value reflects the progress made in the project concerning the project schedule. Consequently, the project activities are on track since the schedule variance is positive, which signifies the
For the Med. Mgr., a degree of monitoring is required at least to ensure that daily production goals are being met, inventory is stocked and clients are satisfied. This requires internal monitoring and occupies a reasonable fraction of the Med. Mgr.'s time. The Bank Mgr. would report that no real monitoring is required other than to ensure that the personnel over which he presides are meeting their respective responsibilities.
Strategic Management at McDonald's McDonald's Strategic Management Strategic Management at McDonald's Strategic Management at McDonald's McDonald's: Introduction Organizational Structure and Corporate Governance Industry Sector Analysis Michael Porter's Five Forces Model Key conditions in the External Operating Environment of McDonald's and its Industry The Value Proposition on McDonald's Products Financial Performance SWOT Analysis for McDonald's TOWS Matrix for Alternative Strategies BCG Growth Share Matrix for McDonald's Marketing, Financial, and Research & Development Strategies McDonald's Leadership Joint Ventures, Strategic Alliances, and Partnerships Performance Measurement Methods and Benchmarks Recommendations References Table of Contents Sr.
risk that Apple Inc. faces with respect to its international economic exposure. Apple designs its products in the United States, manufactures them in China and then sells them all over the world. In order to analyze this exposure, a number of steps will be undertaken. The first step will be to provide an overview of the business, what its foreign exchange exposure is, and how the company manages that
Harley Davidson Strategic Management -- Harley Davidson This work examines the strategic management of Harley Davidson Company and seeks to answer specific questions relating to this company's management through conduction of a Porter's Five Forces analysis and a review of the literature on this company. The specific research questions examined in this study are those as follows: (1) What are the primary competitive forces impacting U.S. motorcycle producers in general and producers like
Supply Chain Management Founded in 1903, Ford Motor Company now manufactures or distributes automobiles across six continents. Ford employs about 164,000 people in about 70 plants worldwide. The company's automotive brands include Ford and Lincoln. According to Ford's corporate website, in 2010 Ford earned $6.6 billion, their highest net income in more than 10 years. In 2010 Ford launched 24 new or redesigned vehicles in key markets around the world. Ford expects
Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.
Get Started Now